Works at Mapledurham Playing Fields for The Heights school

Planning permission granted and legal action dismissed, works on site at Mapledurham Playing Fields began at the end of February.

View from car park over school site
The site in the north west corner abutting the car park was cleared of trees by Kier Construction's contractor, Bennett's Tree Care.

Reading Borough Council (RBC) neatly pruned back the trees along the vehicular access off Chazey Road to give clear access. They then took out the trees around the playground to make way for the works to the playing fields which will enable an intensification of use, ie more football to be played by drainage improvements as well as a levelling of the areas with pitches.

Today (11 March) and tomorrow, Kier will be carrying out soil investigation works as part of the upgrading of the existing car park and access road off the Upper Woodcote Road entrance.

Vacuum excavation plant will be used to locate all the existing services in these areas and complete and record a survey prior to their reinstatement. The areas around the excavation and plant will be enclosed with Heras fencing whilst these works are progressively completed. This plant is powered by the diesel engine of the vehicle and so this will be operating throughout the period it is on site.

Over the 13 and 14 March six trial pit excavations will be completed in the car park area. During these works 6 to 8 car parking spaces will not be available.

Works to relocate the playing field access gate are programmed to start on 14 March and completed by Friday 15 March.

Should anyone wish for further information do let me know as I have further plans showing the relevant areas.