Works to re-start at Mapledurham Pavilion

This afternoon Reading Borough Council (RBC) announced the welcome news that refurbishment of Mapledurham Pavilion will restart on Monday 4 May.
Mapledurham Pavilion's works to restart on 4 May 


Below is the information RBC has provided:

Re Mapledurham Pavilion works
The works to the pavilion started in early March by AYM Services Ltd, but were temporarily put on hold due to Covid-19 and the difficulty in meeting social distancing guidance.

Central Government have identified that where construction work is able to safely continue it should do so to aid future economic recovery. The Government have recently updated its Covid–19 construction safety guidance giving more specific advice on safe working practices. AYM have adjusted their working practices to reflect and meet this updated advice on social distancing rules.

AYM will re-start work on the pavilion on Monday 4th May with a reduced work force to build the small side extension and replace the existing roof and windows. Then the majority of work is inside, refurbishing the interior of the pavilion, for example installing new heating, electrics, changing facilities and toilets.

We have not taken this decision lightly. The pavilion is a community facility that we would like to reopen as soon as we are allowed for local people to use. We are aware of resident concerns about noise, disruption and social distancing caused by other nearby works and have put in place measures to address these concerns for the pavilion works. These include:
  • A smaller workforce to meet revised Covid-19 construction safety guidance and will mean less activity on site at any one time
  • We have asked that AYM work with the Council’s Environment Protection (EP) Team and apply for a S61 noise licence to limit or reduce any noisy work where possible to reflect that there are more people staying at home
  • A noise monitor is to be installed near the pavilion to automatically record noise levels to help the EP Team monitor noise and target any site visits on the pavilion works
  • All compressors and generators, where practicable, will be ‘sound reduced’ models fitted with acoustic covers to remain closed whenever they are in use
  • All plant and machinery are to be fitted with effective silencers where available, will be sited away from houses where practicable, and will be shut down when not in use
  • The AYM site manager will letter drop nearest neighbours to provide information as work progresses and will be available on site to listen to any queries about the pavilion works 

AYM construction working hours are Monday–Friday 8 am - 6 pm and, if needed, Saturday 9 am - 1 pm. They will be arriving on site between 7 am - 8 am to carry out safety checks but are aware that actual construction work is not to start before 8 am.

To help immediate neighbours to the pavilion know what is happening AYM will provide regular updates to them. The site manager of AYM is Michael Leith, AYM site manager and may be contacted by email on Michael.leith@aymservices.co,uk.

For all enquiries relating to the construction of the Heights Primary School, in the first instance please contact the Kier project manager on John.Hempton2@kier.co.uk. While the Department for Education are controlling the works to the Heights School, the Council’s Environment Protection team are also monitoring the school works and may be contacted at environmental.protection@reading.gov.uk For more general information about the Landscape works taking place at Mapledurham Playing Fields, please visit RBC's website page